Kings Square Project, Riyadh
Deep excavation shoring with reinforced concrete pile walls and multiple levels of ground anchors at Kings Square, Riyadh. The selected section shows a 14.5-metre excavation level difference.
Project overview
International Rafedah Piles Company carried out the reinforced concrete pile wall and ground anchor shoring works. The system coordinates vertical retaining members, tie beams and anchor levels with the excavation sequence. Project details address adjacent structures and excavation boundaries through a multi-level engineering arrangement.
- Location
- Riyadh
- Shoring system
- Reinforced concrete pile walls with ground anchors
- Project status
- Completed
- Main contractor
- Al Basateen Real Estate Development Company
- Owner
- Sarh Kas Real Estate Development & Investment Company
- Excavation level difference in as-built section
- 14.5 metres
Site photography
A closer look at the project
From design to construction
An engineering design detail
The as-built section indicates a ground level of −0.15 and a final excavation level of −14.65, giving a 14.5-metre difference. It shows reinforced concrete piles extending below excavation level and inclined ground anchors arranged at multiple levels. The selected excerpt isolates the shoring section without the drawing frame or administrative title block.
Related services
Deep excavation and multi-level support
Kings Square in Riyadh is documented with reinforced concrete pile walls and multi-level ground anchors. The illustrated section records a 14.5 m excavation level difference; the figure refers to that documented section.
From drawing to site
The engineering excerpt shows the retaining and support arrangement, while the available photographs record site conditions and RPC’s works. Reading the section alongside the photographs helps explain the relationship between the reinforced concrete pile walls, anchor levels and support distribution over the excavation depth.
Engineering context
RPC executed excavation shoring using reinforced pile walls and multiple levels of ground anchors. The displayed section shows an excavation level difference of 14.5 m. This figure relates to that section; the project drawings define the arrangement and details of the piles and anchors. Site photographs and drawing excerpts show the relationship between the reinforced pile wall and the support levels.
The next step
Let’s review your site requirements
Share the available drawings, ground investigation report, excavation depth and required scope so we can discuss the requirements and next steps